CDPH has successfully implemented over 4,000 campsite construction services in more than 100 countries.
The challenge of this project was that typical temporary container houses only meet the construction requirements for three stories or less, while this project required the construction of a four-story container dormitory on a steel structure foundation. After careful stress analysis, the company's technical department determined the final solution and provided the client with a qualified written stress calculation report.
Contact Us
Area:Indonesia, Asia
client:GEM Company's dormitory construction project in Indonesia
Room Type:Modular House and Steel Structure
Field:Mining plant uses
Area:30000㎡-60000㎡
Scenes:Dormitory, Private Bathroom, Lounge, Restaurant
Time:2023year



1. Coordinate with factories and supply chains to ensure timely delivery and port access.
2. Add a washing machine drain at the entrance of the prefabricated bathroom to prevent leaks from affecting the room.
3. Seal the gap between the roof beams and floor beams with widened sealing strips to prevent rainwater from entering the roof.
4. Install wiring for wall sockets on the roof, running it through guide rails to prevent wire wear.
5. Replace with multi-functional sockets with round holes for easier on-site use.



Technical features:
1. The dormitory building has five floors. Based on stress calculations, the first floor uses a steel structure, the second to fourth floors use container-style dormitories, and the fifth floor has a drying area and a pitched roof.
2. The roof of the drying area uses polycarbonate panels. Other areas have a steel structure roof truss with red resin tiles.
3. Exterior color design: The container-style house frames are white, and all exterior wall panels are beige.